Kees van der Leun on Nostr: After 17 years of construction (the plan was 4.5 years), 2 years of commissioning, ...

After 17 years of construction (the plan was 4.5 years), 2 years of commissioning, and a few months of operation, France's new nuclear power plant Flamanville 3 is now getting ready for the replacement of its reactor head. It will be out of operation for a year.
https://www.sfeninenglish.org/flamanville-3-new-reactor-vessel-head-arrives-ahead-of-vc1/